  • Property Acquisition Demolition

  • University Blvd. Improvement Project

    Poor Pavement Conditions
  • University Blvd. Improvement Project

    Uninviting Bus Stops
  • University Blvd. Improvement Project

    Lack of Wheelchair Accessible Route
  • University Blvd. Improvement Project

    Heavy Traffic Volumes
  • 1
  • 2
  • 3
  • 4
  • 5

New Updated University Blvd Schematic

Updated University Boulevard Improvement Project

Detailed Project Timeline

(As of August 2017)

Preliminary Design Phase:
January 29 2015 Project Started
Feb. to July 2015 Evaluated various alignment options for University
July 2015 Conducted door-to-door introductions along the corridor
August 6 2015 Held first Public Meeting at Jack Rodgers Auditorium at Odessa College
Aug. to Oct. 2015 Refined alignments based on feedback received at first Public Meeting
November 3 2015 Consultant briefed City Council on the public response
Nov to Dec 2015 Evaluated additional alignment options requested by City Council
January 5 2016 Consultant presented recommended improvements to City Council
January 12 2016 Held second Public Meeting at Odessa City Hall during Council Meeting
February 1 2016 Held third Public Meeting at Jack Rodgers Auditorium at Odessa College
Feb. to June 2016 Developed final strip map and analyzed right-of-way needs.
Final Design and Right-of-way Acquisition Phase:
July 2016

Consultant began process of acquiring right-of-way for the project

Consultant began final design phase

Consultant began coordinating with utility companies for adjustments

Construction Phase:
July 2017 Began Atmos Gas Line Relocation (US 385 to Dixie)
July 2017 Began Full Property Purchase Demolitions
September 2017  Anticipate beginning Atmos Gas Line Relocation (US 385 to Dixie)
October 2017  
December 2017 Anticipate beginning Atmos Gas Line Relocation (Dixie to Maple)
January 2018 Anticipate beginning ROW Clearance and Utility Relocation*
January 2018 Anticipate beginning Atmos Gas Line Relocation (Maple to Grandview)
March 2018 Anticipate ending Atmos Gas Line Relocation (Maple to Grandview)
May 2018 Anticipate ending ROW Clearance and Utility Relocation*
Summer 2018 Anticipate beginning Phase 1 Roadway Construction (US 385 to Maple)*
Summer 2018 Anticipate ending Phase 1 Roadway Construction (US 385 to Maple)*
Summer 2018  Anticipate beginning Phase 2 Roadway Construction (Maple to Grandview)*
Summer 2018  Anticipate ending Phase 2 Roadway Construction (Maple to Grandview)*

 * The anticipated start and end dates for construction are dependent upon the schedule for right-of-way and/or easement acquisitions. Dates may be adjusted to accommodate the acquisition of all right-of-way and/or easements that are needed to begin a particular phase of construction.

 Overview Project Timeline

(As of August 2017)

Preliminary Design Phase:
January 29 2015 Project Started
Feb. to July 2015 Evaluated various alignment options for University
Aug to Oct 2015 Refined alignments based on feedback received at first Public Meeting
Nov to Dec 2015 Evaluated additional alighment options requested by City Council
Feb to June 2016 Developed final strip map and analyzed right-of-way needs
Final Design and Right-of-way Acquisition Phase:
July 2016

Began right-of-way acquisition

Began final design phase

Construction Phase:
July '17 - Mar '18   Atmos Gas Line Relocation (US 385 to Grandview)*
July 2017   Began Full Property Purchase Demolitions
Jan '18 - May '18   ROW Clearance and Utility Relocation*
Summer '18 - '19  

Phase 1 Roadway Construction (US 385 to Maple)*

Summer '19 - '20   Phase 2 Roadway Construction (Maple to Grandview)*

* The anticipated start and end dates for construction are dependent upon the schedule for right-of-way and/or easement acquisitions. Dates may be adjusted to accommodate the acquisition of all right-of-way and/or easements that are needed to begin a particular phase of construction.

2701 Century


Click to View

The home at 2701 Century has been purchased and cleared in anticipation of upcoming roadway improvements to be made along University Boulevard.

Other properties that are scheduled for acquisition and clearing for this project include:

  • 2700 Eastover
  • 2701 Eastover
  • 2408 Walnut
  • 2700 Windsor
  • 2701 Windsor
  • 3401 University2404 Nabors

If you have any questions, pllease don't hesitate to contact us by phone @ 432-614-1742 or sending a message using the feature below!

Contact Us

Questions/Comments

If you would like to get more information about this project or have any questions, fill out the form below.
captcha
Reload